First batch of Three Gorges Guangdong 300MW offshore wind farm turbines go on-grid

First batch of Three Gorges Guangdong 300MW offshore wind farm turbines go on-grid

38

The Three Gorges Yangxishaba offshore wind farm, which has just completed grid connection of its first batch of wind turbines, is located in Yangjiang City, about 28km from shore where water depth is 27-32m.

The project consists of 55 units of 5.5MW offshore wind turbines for an installed capacity of 300MW, with plans to reach full production capacity by the end of 2020. (CTGNE)