On March 30, heavy trucks loaded with 10MW offshore wind turbines with Asia’s largest single-unit capacity drove out of Dongfang Wind Power’s Fujian manufacturing base and headed towards Fujian Jiangyin Port Deep Sea Wharf.
In a few days, they will be transported by large barges to Fujian Changle Offshore Wind Farm A and C for hoisting.
Fujian Changle Area A and C, developed by Three Gorges Group and Funeng Group respectively, are located 32-40km off the coastline of Changle District. The Three Gorges Group Changle Offshore Wind Farm Area A project is the first batch of Dongfang Electric’s 10MW offshore wind turbines. In the project, 10 units of 10MW offshore typhoon-resistant wind turbines will be installed. The Funeng Group Fujian Changle Offshore Wind Farm C Zone 200MW project will install 20 units of Dongfang Electric 10MW offshore typhoon-resistant wind turbines. Both projects are scheduled to be put into operation before October this year.