CGN Shengsi 6# Offshore Wind Project’s first batch of turbines have been connected to the grid

CGN Shengsi 6# Offshore Wind Project’s first batch of turbines have been connected to the grid

58

The CGN Shengsi 5#&6# Offshore Wind Farm has successfully connected its first batch of turbines to the grid.

The project was approved in January 2019 and began construction in August 2019. Located to the east of Donghai Bridge, about 10km off the coast of Xiaoyangshan Island, the wind farm is supplied by a 220kV submarine power cable. The wind farm, composed of 47 units of 6.0MW offshore wind turbines, has a total investment of CNY 4.8 billion. At full operating capacity, it is estimated to generate an annual output of about 827GWh.

(ZJOL)